The removal process has resumed on RE-2 Road in Indore: 130 obstructing houses are being demolished. The Municipal Commissioner and senior officials are present at the scene with a large police force.

1 sourceFriday, October 9

The administration and the municipal corporation have once again initiated the removal process to complete the construction of the incomplete portion of RE-2 Road (Ring Road East-2) between Bengali Chauraha and Piplihana. Since Thursday morning, the corporation team has been engaged in removing houses obstructing the road construction, with a heavy police presence. During the action, the remaining 130 obstructing houses are being demolished. The action is currently underway at the site.

Source articles